Birmingham court orders demolition of three Southside buildings
A consent order requires the owner of vacant properties to clear debris and begin asbestos surveys within days.
By Mateo Castillo ·

A Jefferson County judge signed a consent order on Nov. 16 that requires the owner of three vacant buildings in Birmingham's Southside district to demolish them. The agreement resolves a lawsuit filed by the city of Birmingham against LPOTP, LLC, which controls the properties at 1923 First Avenue South, 1922 Second Avenue South, and 110 20th Street South.
The court ruling mandates that the owner remove debris from the interior and exterior of the sites within 15 days of signing the agreement. Entrances to the buildings must be secured within 30 days. The owner is also required to start an asbestos inspection of all structures during the week of Nov. 16.
Demolition must be completed at the owner's expense within 120 days, with the exception of a specific portion of one building that will be sold. The order does not identify which section of the structure is designated for sale. The owner must retain a licensed and bonded demolition company within 90 days. The Design Review Committee will conduct an expedited review to approve the demolition plans.
City attorney Nicole King stated that the agreement represents a day when the city and a property owner work together to turn a problem property into a positive asset. "It's a great day for the citizens of Birmingham when the City, through court action, can work together with the owner of a nuisance property to show accountability for turning their problem property into a positive asset," King said in a statement on Friday.
The city filed its lawsuit on Nov. 5, seeking a declaration that the properties were public nuisances. Officials cited multiple incidents, including a fire on March 23 inside the building at 1923 First Avenue South. They also noted that a man shot on Nov. 1 died inside one of the buildings after retreating there. The city claimed the owner was notified of code violations in September 2025 and January 2026, but the sites remained vacant and accessible to the public.
Under the terms of the order, the city will waive court costs and attorney fees. It will stop further legal action against the owner if the conditions are met. The court will keep jurisdiction for at least 18 months to monitor compliance. The owner must submit a status report to the city every 30 days, with the first report due around Dec. 13.